"40 years in bulk materials handling and the construction industry"

CE Mark Image

Member of the Avetta Consortium - click to view certificate

19
JUN
2019

90 Building Extension

  Centristic has begun the erection of a major extension to the 90 Building for a clay processing company near Newton Abbot. The 200 tonne structure is part of the Roller Mill project which also includes an in feed building and a gantry conveyor. The extension, internal...
07
FEB
2019

Investment at Centristic Ltd – New 10t Workshop Crane

Centristic are pleased to announce that they have successfully completed the installation and commissioning of their new 10/T SWL Gantry crane The new 12 metre span gantry crane has been successfully installed by our own team in our recently extended fabrication workshops at...
15
JAN
2018

Brett Aggregates Ltd – Queen Mary Quarry – New Sand & Gravel Processing Plant

In early 2017 Centristic were delighted to be awarded the contract to design, fabricate and erect a new sand and gravel processing plant for Brett Aggregates Ltd at their Queen Mary Quarry site in Middlesex. This was Centristic’s first project working for Brett and were looking...
23
NOV
2017

Centristic Workshop Expansion

Following on from the recent success of a number of projects and with the rest of the year looking full of prospects, it was decided that the Centristic workshop would be expanded to increase work capacity; and be in a position to be able to work on larger fabrications. Planning...
01
NOV
2017

Kempsford Quarry Sand Plant – Aggregate Industries, Manor Farm

Aggregate Industries Limited, Kempsford Quarry, United Kingdom operated a sand & gravel processing plant last re-equipped in 1987 with the installation of screening & washing facilities for up to 200 K tonnes per annum. Centristic won the contract to modify the existing...
23
OCT
2017

Stainless & Glass Balustrade to Four Storey Feature Staircase in Plymouth

Working with our customer a low maintenance, compliant balustrade & handrail system was required for a feature staircase within a new build student facility in Plymouth. Stainless steel with a satin finish was selected due to its low maintenance properties together with 10mm...
14
AUG
2017

Centristic Excellence in Health & Safety Award – NHBC

Centristic are proud to announce that we have been presented with the H&S certificate by the NHBC whilst working on behalf of Kier Living on the North Prospect development in Plymouth. This certificate can be seen here. The development consists of over 150 new houses and...
13
JUN
2017

Steel Spire fitted to top of Plymouths Tallest Building

Centristic ltd in Newton Abbot, Devon were commissioned by Kier Construction to detail draw, fabricate & install the Hot Dip Galvanised steel structure that forms the Spire to Plymouth’s tallest building. It is a significant landmark project making it one of the tallest...
09
JAN
2017

Sports Hall Completed for Richard Huish – Taunton

Over 85 tons of structural steel frame for the Richard Huish Sports Hall, Taunton is now complete with the project successfully handed over to the client. Centristic have detailed, drawn, fabricated, painted all parts of the sports hall frame, and then had a technically...
06
JAN
2017

New Feature Stair Cases for Plymouth Science Park

In April 2016 Centristic were awarded the secondary steelwork package by BAM Construction for the Plymouth Science Park Phase 5 new development. Various secondary steelwork were with the scope of works, with the most notable being the two internal feature staircases with glazed...