"40 years in bulk materials handling and the construction industry"

CE Mark Image

Member of the Avetta Consortium - click to view certificate

28
NOV
2019

EXECUTION CLASS 3

Centristic are very pleased to announce the successful surveillance and subsequent uprating of our CE marking to Execution Class 3. This means that we can now offer bridge structure fabrication as well as stadia, if our clients should require. To view our full certificate click...
21
NOV
2019

Update – Roller Mill Extension

Over the last few months Centristic’s in house installation team have been erecting the Roller Mill extension building, gantry conveyor and infeed building for a major clay processing company at one of their Newton Abbot sites. The two buildings and gantry are comprised of...
02
OCT
2019

New Apprentices at Centristic

At Centristic we are keen to inspire, encourage and educate young minds and prepare them for success in future careers. On the back of previous successful Apprenticeship engagement, we have taken on 5 new Apprentices to learn and work alongside our drawing office and fabrication...
18
JUL
2019

Work Experience at Centristic

This Week on a work experience placement, year 10 student Ross Harvey from Coombeshead Academy, Newton abbot, has been learning to use our 3D Computer Design Package, Tekla Structures. Mainly working with the design and detailing team Ross has also had the opportunity to visit...
19
JUN
2019

90 Building Extension

  Centristic has begun the erection of a major extension to the 90 Building for a clay processing company near Newton Abbot. The 200 tonne structure is part of the Roller Mill project which also includes an in feed building and a gantry conveyor. The extension, internal...
07
FEB
2019

Investment at Centristic Ltd – New 10t Workshop Crane

Centristic are pleased to announce that they have successfully completed the installation and commissioning of their new 10/T SWL Gantry crane The new 12 metre span gantry crane has been successfully installed by our own team in our recently extended fabrication workshops at...
15
JAN
2018

Brett Aggregates Ltd – Queen Mary Quarry – New Sand & Gravel Processing Plant

In early 2017 Centristic were delighted to be awarded the contract to design, fabricate and erect a new sand and gravel processing plant for Brett Aggregates Ltd at their Queen Mary Quarry site in Middlesex. This was Centristic’s first project working for Brett and were looking...
23
NOV
2017

Centristic Workshop Expansion

Following on from the recent success of a number of projects and with the rest of the year looking full of prospects, it was decided that the Centristic workshop would be expanded to increase work capacity; and be in a position to be able to work on larger fabrications. Planning...
01
NOV
2017

Kempsford Quarry Sand Plant – Aggregate Industries, Manor Farm

Aggregate Industries Limited, Kempsford Quarry, United Kingdom operated a sand & gravel processing plant last re-equipped in 1987 with the installation of screening & washing facilities for up to 200 K tonnes per annum. Centristic won the contract to modify the existing...
23
OCT
2017

Stainless & Glass Balustrade to Four Storey Feature Staircase in Plymouth

Working with our customer a low maintenance, compliant balustrade & handrail system was required for a feature staircase within a new build student facility in Plymouth. Stainless steel with a satin finish was selected due to its low maintenance properties together with 10mm...